- Ensure that the project is completed within budget Concerned with cost of resources needed to complete activities; consider effect of project decisions on cost of using product “life-cycle costing”
- Most prospective financial impact of using the product is outside the project scope
- Consider information needs of stakeholders, controllable and uncontrollable costs (budget separately for reward and recognition systems)
- Estimating should be based on WBS to improve accuracy
- Estimating should be done by the person performing the work
- Having historical records is key to improving estimates
- Costs (schedule, scope, resources) should be managed to estimates
- A cost (schedule, scope, baseline) should be kept and not changed
- Plans should be revised as necessary during completion of work
- Corrective action should be taken when cost problems (schedule, scope and resources) occur.
Determining what physical resources and quantities are needed to perform work
Inputs to Resource Planning:
- Work Breakdown Structure
- Historical Information
- Scope Statement – justification & objectives
- Resource Pool Description – what resources are potentially available for resource planning
- Organizational Policies – staffing, procurement
- Work Breakdown Structure
- Network Diagram
- Schedule
- Risks
- Historical Information
- Scope Statement – justification & objectives
- Resource Pool Description – what resources are potentially available for resource planning
- Organizational Policies – staffing, procurement
Resource Planning Tools & Techniques
- Expert Judgment
- Alternatives Identification
Resource Planning Outputs:
Resource Requirements – what type & how many resources are needed for each activity in the Work Breakdown Structure
Cost Estimating:
- Develop approximate costs of resources
- Distinguish estimating from pricing
- Estimating – likely amount
- Pricing – business decision
- Identify alternatives and consider realigning costs in phases to their expected savings
Cost Estimating Inputs:
- Work Breakdown Structure
- Resource Requirements
- Resource Rates (if known)
- Activity Duration Estimates
- Historical Information – (project files, commercial cost databases, team knowledge
- Chart Of Accounts – coding structure for accounting; general ledger reporting
Cost Estimating Tools & Techniques
- Analogous Estimating – “top down”; using actual costs from previous project as basis for estimate
- Reliable when previous projects are similar and individuals have expertise – form of expert judgment
- Parametric Modeling – uses project characteristics in mathematical models to predict costs (e.g.building houses)
- Reliable when historical information is accurate, parameters are quantifiable, and model is scalable
- 2 types: Regression analysis, Learning Curve
- Bottom Up Estimating – rolling up individual activities into project total – smaller work activities have more accuracy -
- Computerized tools – spreadsheets, software
- Pro’s and Con’s
- Analogous Estimating
- Quick - Less Accurate
- Tasks don’t need to be identified – Estimates prepared with little detail and understanding of project
- Less costly – Requires considerable experience to do well
- Gives PM idea of management expectations – Infighting at high levels of organization
- Overall project costs are capped – Difficult for projects with uncertainty
- Bottom Up Estimating
- More Accurate – Takes time and expense
- Gains buy-in from the team – Tendency for team to pad estimates
- Based on detailed analysis of project – Requires that project be defined and understood
- Provides a basis for monitoring and control – Team infighting to get biggest piece of pie
Outputs from Cost Estimating
- Cost estimates – quantitative assessments of likely costs of resources required to complete tasks
- For all resources of the project (labor, materials, supplies, inflation allowance, reserve)
- Expressed in units of currency
- Supporting Detail
- Description of scope (reference to the WBS)
- Documentation how estimate was developed
- Indication of range of possible results
- Assumptions
- Cost Management Plan – how cost variances will be managed
- Cost Risk: associated to seller for Fixed Price; associated to buyer for Time and Materials budget
Cost Budgeting
Involves allocation of total estimate to individual work to establish a cost baseline to measure performance
Cost Budgeting Inputs
same as Cost Estimating Tools and Techniques
Outputs from Cost Budgeting
Involves allocation of total estimate to individual work to establish a cost baseline to measure performance
Cost Budgeting Inputs
- Cost Estimate
- Work Breakdown Structure
- Project Schedule – includes planned start and finish dates for items costs are allocated to
- Needed to assign costs during the time period when the actual cost will be incurred
same as Cost Estimating Tools and Techniques
Outputs from Cost Budgeting
- Cost Baseline – time phased budget to measure and monitor cost performance
- Developed by summing estimated costs by period (S curve of values vs. time)
- Larger projects have multiple baselines to measure different aspects of cost performance
Cost Control
- Concerned with influencing factors that create changes to the cost baseline that are beneficial
- Determining that the cost baseline has changed
- Managing actual changes as they occur
- Monitor cost performance to detect variances
- Record all appropriate changes accurately in the cost baseline
- Preventing incorrect, unauthorized changes being included in the cost baseline
- Informing stakeholders of authorized changes
- Determine the “why’s” of positive and negative variances
- Integrated will all other control processes (scope, change, schedule, quality)
Inputs to Cost Control
- Cost Baseline
- Performance Reports – meet, exceed budget
- 50/50 Rule – task is considered 50% complete when it begins and gets credit for remainder 50% only when completed
- 20/80 Rule - task is considered 20% complete when it begins and gets credit for remainder 80% only when completed
- 0/100 Rule – task only credited when fully completed
- Change Requests
- Cost Management Plan
Tools & Techniques of Cost Control
- Cost Change Control System – defines the procedures by which the cost baseline may be changed
- Performance Measurement – assess magnitude of cost variations (Earned Value Analysis) and what is causing the variance
- Additional Planning – examine alternatives
- Computerized Tools – forecast planned costs, track actual costs, forecast effect of cost changes
Cost Control Outputs
- Revised Cost Estimate
- Modifications to cost information; require stakeholder approval and adjustments to other project areas
- Budget Updates – changes to approved cost baseline; revised in response to scope changes
- Corrective Action
- Estimate at completion – (EAC) – forecast of total expenditures
- Actual to date plus remaining budget modified by a factor (cost performance index)
- Current variances are seen to apply to future variances
- Actual to date plus new estimate for remaining work
- Original estimates are flawed, or no longer relevant
- Actual to date plus remaining budget
- Current variances are typical and similar variances will not occur in the future
- Lessons Learned
Earned Value Analysis
- Integrates cost, schedule and scope
- Better that comparing projected vs. actual because time and cost are analyzed separately
- Terms:
- BCWS – Budgeted Cost of Work Scheduled (how much work should be done)
- BCWP – Budgeted Cost of Work Performed a.k.a. Earned Value (how much work is budgeted, how much did we budget)
- ACWP – Actual Cost of Work Performed (how much did the completed work cost)
Earned Value Analysis
- Terms:
- BAC – Budget at Completion (how much did you budget for the total job)
- EAC – Estimate at Completion (what do we expect the total project to cost)
- ETC – Estimate to Completion (how much more do we expect to spend to finish the job)
- VAC – Variance at Completion (how much over/under budget do we expect to be)
- Formulas
- Variance (Plan – Actual)
- Cost Variance (CV): BCWP – ACWP; negative is over budget
- Schedule Variance (SV): BCWP – BCWS; negative is behind schedule
- Cost Performance Index (CPI): BCWP / ACWP
- I am only getting x¢ out of every $
- Schedule Performance Index (SPI): BCWP / BCWS
- I am only progressing x % of the planned rate
- Estimate at Completion (EAC): BAC / CPI
- As of now we expect the total project to cost x$
- Estimate to Complete (ETC): EAC – ACWP; how much will it cost from now to completion
- Variance at Completion: BAC – EAC; when the project is over how much more or less did we spend (most common way of calculating EVA)
- BCWP comes first in most formulas
- If it is a variance, BCWP comes first
- If it is an index, BCWP is divided by
- If the formula relates to cost, use AWCP
- If the formula related to schedule, use BWCP
- Negative is bad; positive results are good
- ETC refers to “this point on”; EAC refers to when job is completed
Accuracy of Estimates
- Order of Magnitude Estimate: -25% - 75%; usually made during Initiation Phase
- Budget Estimate: -10% - 25%; usually made during the Planning phase
- Definitive Estimate: -5% - 10%; usually made during the Planning phase
Accounting Standards
- Not usually part of the exam
- Present Value (value today of future cash flows):
- PV = FV/[ (1 + r) N]
- FV = Future Value
- R = Interest Rate
- N = Number of time periods
- Net Present Value: total benefits (income or revenue) less the costs. NPV is the sum of each present value of each income/revenue item
- Internal Rate of Return (IRR): company may select project based on highest IRR
- Payback Period: number of time periods it takes to recover the investment in the project before generating revenues
- Benefit Cost Ratio (BCR): compares costs to the benefits of different projects
- Greater than 1 means benefits are greater than costs
- Less than 1 means costs are greater than benefits
- Opportunity Cost: opportunity given up by selecting one project over another
- Sunk Costs: expended costs. Sunk costs should not be considered when determining to continue with a troubled project
- Law of Diminishing Returns: the more that is put in the less of an outcome is received
- Working Capital: current assets – current liabilities
- Variable Cost: costs that change with the amount of production or the amount of work (materials, wages)
- Fixed Cost: non-recurring costs that do not change
- Direct Cost: directly attributable to project work (travel, wages, materials)
- Indirect Cost: overhead items or costs for the benefit of more than one project (taxes, fringe benefits)
- Depreciation: assets lose value over time
- Straight Line depreciation: same amount is taken each year
- Accelerated Depreciation: 2 forms
- Double Declining Balance
- Sum of the Years Digits
- Life Cycle Costing: includes operations and maintenance phases
- Value Analysis: find a less costly way to do same work
- Make or Buy decisions –at Development (Planning) phase, not conceptual phase
- Project Objectives – are not necessarily needed to fund project
- Project Definition – focus on end product initially; costs and benefits will be evaluated later
- 25% of project lifecycle expended at end of planning
- No guarantees; only most likely results
- Line of Balance charts are used for manufacturing
- Negative Float – the late start date is earlier than the early start date
- Value Engineering/analysis – does not trade performance for cost
- Prospectus – profitability and technical feasibility used to solicit funding